Mining Show 2025
Grindrod
Central AfricaCommoditiesCopperNewsProjects

Stage Two dewatering of the Kakula Mine has commenced on schedule

Ivanhoe Mines’ has announced that following the last update made on August 25, 2025, the Stage Two dewatering of the Kakula Mine has commenced on schedule, and that Kamoa-Kakula’s 2026 and 2027 copper production guidance will now be issued once Stage Two dewatering activities are more advanced.

Three out of the four Stage Two high-capacity, submersible pumps were recently installed and commissioned on schedule. Kamoa-Kakula’s engineering team expect to have all four Stage Two pumps operating within the coming days, operating at a combined pumping rate of approximately 2,600 litres per second. Since the commissioning of the three Stage Two pumps, the underground water level in the Kakula Mine has dropped vertically by 10 metres, out of a total of approximately 80 metres.

Once all four Stage Two high-capacity, submersible pumps are operational, the existing Stage One temporary, underground pumping infrastructure will be repositioned further down the mine, following the water level as it declines. The total pumping rate out of the Kakula Mine is expected to increase up to a target of approximately 6,400 litres per second, or 550 megalitres per day, reducing the vertical underground water level by approximately one metre per day. The majority of the Stage Two dewatering of the Kakula Mine is expected to be complete by the end of November 2025, which is when the underground water level is expected to reach near the bottom of the Stage Two dewatering shafts, shown in yellow in Figure 1.

Suppliers Directory2026

As the underground water level falls, the underground mining team have already started systematically rehabilitating the newly dewatered areas of the Kakula Mine. The team is initially focused on rehabilitating the areas required for repositioning the Stage One underground pumping infrastructure.

Mine planning and scheduling is well advanced to support the ramp-up of underground mining activities from both Kakula and Kamoa mines, with a medium-term target of returning the copper production rate to over 550,000 tonnes per annum. In the meantime, copper production guidance for 2026 and 2027 will be deferred until sufficient physical inspection of the newly dewatered areas of the Kakula Mine has been completed.

Dewatering Kakula
[Figure 1]: A schematic of the projected decrease in underground water levels at the Kakula underground mine from early September (light blue) to late November 2025 (dark blue). All mining areas above the water level are now fully accessible.
The completed assembly of the first two, 4.2-megawatt, 650-litre-per-second, submersible pumps (Pumps 1 & 2) that were commissioned in late August. The two submersible pumps are positioned at the bottom of the approximately 400-metre deep shaft (left of the picture).

Water pumped out from the Kakula Mine is fed into nearby settling ponds for treatment. With the underground vertical water level expected to decline by approximately one metre per day, the majority of the Stage Two dewatering of the Kakula Mine is expected to be complete by the end of November 2025.

At an adjacent ventilation shaft, the installation of the remaining two submersible pumps (Pumps 3 & 4) is complete, with commissioning of Pump 4 underway. Kamoa-Kakula’s engineering team expect to have all four Stage Two pumps operating within the coming days.

Want more stuff like this?

Join over 65, 400 subscribers and receive our weekly newsletter!

SRK

Staff Writer

The African Mining Market is a source of insightful information on mining & industrial markets, and developments in Africa.
Back to top button