Marketing is a journey - Let us keep you moving and expanding

Subscribe today →
BME
SRK
CommoditiesCompany NewsLithiumNewsProjectsSouthern Africa

Premier African Minerals to begin 2nd phase of the plant test at Zulu lithium and tantalum project

Premier African Minerals Ltd. will today begin the second phase of the plant test at the Zulu lithium and tantalum project in Zimbabwe.

The company aims to reach a steady state of operation and maintain plant availability of 22 days per month.

“At present the OEM and Zulu personnel are conducting inspections, normal maintenance, and a minor change to flow control in the spodumene float section in advance of this second test run,” said chief executive George Roach.

AFNIS 2026

“Some operating parameter changes and the possible reintroduction of an additional reagent successfully used in 2024, to the extent necessary, round out the preparations.

“Our expectation remains that this will see another major step forward in the optimisation process.”

Want more stuff like this?

Join over 65, 400 subscribers and receive our weekly newsletter!

MMEC 2026
Back to top button